Question: Problem 2 a . Update the ES and EF for A , B , C , E , F , D , and H using
Problem
a Update the ES and EF for A B C E F D and H using the updates below as the end of day show the updated values right on the above network
Activity C will start in days
Activity F has days remaining
Activities A and were on schedule
No changes in the production rate and duration of the activities reported b What could be the predecessor of F according the asbuilt schedule?