Question: Problem 2 a . Update the ES and EF for A , B , C , E , F , D , and H using

Problem 2
a. Update the ES and EF for A, B, C, E, F, D, and H using the updates below as the end of day 18(show the updated values right on the above network).
-Activity C will start in 2 days
-Activity F has 13 days remaining
Activities A and B were on schedule
No changes in the production rate and duration of the activities reported b. What could be the predecessor of F according the as-built schedule?
 Problem 2 a. Update the ES and EF for A, B,