Question: Problem 2 . An assembly line is to operate eight hours per day with a desired output 2 4 0 units per day. The following
Problem
An assembly line is to operate eight hours per day with a desired output units per day. The
following table contains information on this product's task times and precedence relationships:
TASK TIME IMMEDIATE
a Draw the precedence diagram.
b What is the workstation cycle time required to produce units per day?
c Balance this line using the longest task time. Use largest number of following tasks as a secondary
tiebreaker rule. You need to show all the assignments to the workstations and the order in which
you assign tasks.
d What is the efficiency of your line?