Question: Problem 2. An electric car company operates a manufacturing facility. The process produces some 300 vehicles each week. It takes a car about 5 days

Problem 2. An electric car company operates a manufacturing facility. The process produces some 300 vehicles each week. It takes a car about 5 days to move from the beginning of the process to the end. The plant operates for 8 hours per day, 5 days a week. What is the cycle time (in minutes) of the process?

Question 1. What is the capacity of this facility in term of cars per hour? (enter ONLY number)

Question 2. What is the cycle time of this facility in minutes? (enter ONLY number)