Question: Problem 2 (Chapter 5 Project Management). Recently, you were assigned to manage a project for your company. You have constructed a network diagram (depicting the
Problem 2 (Chapter 5 Project Management). Recently, you were assigned to manage a project for your company. You have constructed a network diagram (depicting the various activities in the project, see figure below). In addition, you have asked your team to estimate the amount of time (in days) that they would expect each of the activities to take. Their responses are shown in the table below. (Hint: This problem is similar to the examples in Slides 4150 of Chapter 5) a. What is the expected time and variance for each activity? b. What is the expected completion time of the project? c. What is the probability of completing the project in 20 days? d. What is the probability of completing the project in 18 days
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts