Question: Problem 2 : For a construction site in Fresno, an engineer designed a square footing with B = 3 f t and D f =

Problem 2: For a construction site in Fresno, an engineer designed a square footing with B=3ft and Df=2ft, and is expected to carry 10 kips of load. Estimate the settlement of the foundation using Schmertmann method. Given: concrete=150pcf. The first layer of soil extends from ground level to 8ft and has the unit weight, soil=115pcf, The second layer of soil extends from 8ft to 12ft and has the unit weight, soil=120pcf. Assume time =2yrs after the construction.
(25 points)