Question: Problem 2 (Make sure to draw the time line for the project) (Show all work for full credit) The following cash flows are given for
Problem 2 (Make sure to draw the time line for the project) (Show all work for full credit) The following cash flows are given for Project A. The Project A requires an initial investment of $24,000 in time '0' Year Project A $5,000 6,000 8,000 9,000 6,000 (a) Calculate the NPV for the project using a discount rate of 10.5%. (b) Calculate the IRR for the project (c) Calculate the payback period for the project, FALL