Question: Problem ? 2 Network ( the Crashing based problem ) Problem 2 ( 4 POINTS ) A construction project has a deadline of 2 5
Problem Network the Crashing based problem Problem POINTS
A construction project has a deadline of weeks. And there is a penalty of $ for every week the project is
delayed after weeks. The activities in the project, their sequence relationships, and their expected normal times
are shown in the network. The activities, their expected normal times, and their crash costs are shown in the table
below.
Note: There are paths in this network Networks sent to you as a pdf file
Crash Costs $
a Determine the minimum cost crashing plan to minimize the penalty. List in the correct order all the
activities that will be selected in this plan. Obviously, you will continue to crash only as long as the weekly
crash costs are less than the weekly penalty. points
b Determine the total savings from penalty for the above case. point
Hint for b: For example, if you spend $ to crash a project by one week, and if your penalty is $ for
one week, then your savings from penalty are $ for that week.
Hint: There are FOUR paths in this network I am giving this information so that you minimize your errors
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock