Question: Problem ? 2 Network ( the Crashing based problem ) Problem 2 ( 4 POINTS ) A construction project has a deadline of 2 5

Problem ?2 Network (the Crashing based problem) Problem 2(4 POINTS)
A construction project has a deadline of 25 weeks. And there is a penalty of $50,000 for every week the project is
delayed after 25 weeks. The activities in the project, their sequence relationships, and their expected normal times
are shown in the network. The activities, their expected normal times, and their crash costs are shown in the table
below.
Note: There are 4 paths in this network (Networks sent to you as a pdf file).
Crash Costs ( $000)
(a) Determine the minimum cost crashing plan to minimize the penalty. List (in the correct order 0 all the
activities that will be selected in this plan. Obviously, you will continue to crash only as long as the weekly
crash costs are less than the weekly penalty. (3.5 points)
(b) Determine the total savings from penalty for the above case. (12 point)
Hint for (b): For example, if you spend $10,000 to crash a project by one week, and if your penalty is $50,000 for
one week, then your savings from penalty are $40,000 for that week.
Hint: There are FOUR paths in this network (I am giving this information so that you minimize your errors).
 Problem ?2 Network (the Crashing based problem) Problem 2(4 POINTS) A

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!