Question: Problem 2 . Tesla operates another manufacturing facility. The process produces 2 , 6 8 8 vehicles each week. It takes a car about 5

Problem 2. Tesla operates another manufacturing facility. The process produces 2,688 vehicles each week. It takes a car about 5 days to move from the beginning of the process to the end. The plant operates for 16 hours per day, 5 days a week. What is the cycle time in terms of minutes of this process? (please keep 4 decimal places if it is not integer number)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!