Question: Problem 2 The lead time is one week, and the demand time fence is at the end of week 3. There are 20 on hand.

Problem 2

The lead time is one week, and the demand time fence is at the end of week 3. There are 20 on hand. If the lot size is 20, complete the following problem. Please show work.

Lot size = 20 units

Beg. Inventory is = 20 units

Period 1 2 3 4 5 6
Forecast 20 21 22 20 28 25
Customer Orders 19 18 20 18 30 22
Projected Available Balance =20
MPS
ATP