Question: Problem 2 - Use of sublayers Predict the total settlement ( S ) of the footing shown below. Include contributions from both settlement of the

Problem 2- Use of sublayers
Predict the total settlement (S) of the footing shown below. Include contributions from both settlement of the natural sand layer (use the maximum settlement value) and consolidation settlements. Use superposition of the settlements to determine the total ultimate settlement. Immediate settlement (Si) is not an issue because the footing is resting on the sand layer.
Use two sublayers of equal 10 ft thickness in the CL layer with the undisturbed samples located at the mid height of the layers. Use the appropriate stress chart to determine v in the CL layer and please show your stress diagrams with profiles of vo',v and f' over the entire depth (i.e. both sand and CL soil). The change in soil from sand to clay does not influence the determination of v. Use superposition of the sublayer settlements to determine the total ultimate settlement.
How many days does it take for Uave to reach 90%? We ignore sublayers when evaluating time rate, just use one 20 ft layer.
q=3,000 psf =1.5 tsf
Square footing: B=L=7ft7ft
SP layer: m=105pcf
Sample 1:
Sample depth =5ft below top of CL soil
p'=900psf
e0=1.0
Cc=0.4;Cr=0.04
sat=114.5pcf
Sample 2:
Sample depth =15ft below top of CL soil
p'=1,100psf
e0=1.2
Cc=0.4;Cr=0.04
sat=110pcf
Cv=20ft2yr
when comparea to the CL soll adove)
Problem 2 - Use of sublayers Predict the total

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!