Question: Problem 2: You are given the following project network. In each hexagon, the top number is activity number and the bottom number is the activity

Problem 2: You are given the following project

Problem 2: You are given the following project network. In each hexagon, the top number is activity number and the bottom number is the activity time, in weeks. Determine (i) the critical path and (ii) the number of weeks the project is expected to take. 11 20 16 7 12 6 14 2 Finish Start 12 12 5 17 3 3 15 30 13 6 16 10 21