Question: PROBLEM# 2 ( You MUST show all formules, calculations, and work, and please highlight all answers ) A company is using Kanban containers. There are
PROBLEM#
You MUST show all formules, calculations, and work, and please highlight all answers
A company is using Kanban containers. There are two adjacent work centers, a downstream using and an upstream
producing one. The using work center has a production rate of parts per day and each container holds
parts. It takes days for a container to make the entire cycle from the time it leaves the upstream center until it is
retumed, filled with production, and leaves again. The manager wants a safety factor of The company is
interested in reducing the number of containers.
What is the number of containers currently in
use?
If the number of parts a container holds is
increased to parts, how many containers
are needed?
If the company wants the number of
containers holding parts each to be
what must the safety factor become?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock