Question: Problem 2-21 Plantwide Versus Multiple Predetermined Overhead Rates [LO2-1, LO2-2] Mason Company has two manufacturing departmentsMachining and Assembly. The company considers all of its manufacturing

Problem 2-21 Plantwide Versus Multiple Predetermined Overhead Rates [LO2-1, LO2-2]

Mason Company has two manufacturing departmentsMachining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect to Jobs A and B:

Estimated Data Machining Assembly Total
Manufacturing overhead $ 8,228,000 $ 484,000 $ 8,712,000
Direct labor hours 22,000 374,000 396,000
Machine hours 374,000 17,000 391,000

Job A Machining Assembly Total
Direct labor hours 5 10 15
Machine hours 11 2 13

Job B Machining Assembly Total
Direct labor hours 4 5 9
Machine hours 12 3 15

Required:

1. If Mason Company uses a plantwide predetermined overhead rate with direct labor-hours as the allocation base, how much manufacturing overhead cost would be applied to Job A? Job B? (Round your answers to the nearest whole dollar amount.)

2. Assume that Mason Company uses departmental predetermined overhead rates. The Machining Department is allocated based on machine-hours and the Assembly Department is allocated based on direct labor-hours. How much manufacturing overhead cost would be applied to Job A? Job B? (Round your intermediate calculations and final answers to 2 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!