Question: Problem 2-2A (Algo) Computing and recording job costs; preparing schedule of cost of goods manufactured LO P1, P2, P3, P4 Skip to question [The following
Problem 2-2A (Algo) Computing and recording job costs; preparing schedule of cost of goods manufactured LO P1, P2, P3, P4
Skip to question
[The following information applies to the questions displayed below.] Marco Company shows the following costs for three jobs worked on in April.
| Job 306 | Job 307 | Job 308 | |
|---|---|---|---|
| Balances on March 31 | |||
| Direct materials used (in March) | $ 31,000 | $ 37,000 | |
| Direct labor used (in March) | 23,000 | 18,000 | |
| Overhead applied (March) | 11,500 | 9,000 | |
| Costs during April | |||
| Direct materials used | 131,000 | 210,000 | $ 115,000 |
| Direct labor used | 102,000 | 155,000 | 102,000 |
| Overhead applied | ? | ? | ? |
| Status on April 30 | Finished (sold) | Finished (unsold) | In process |
Additional Information
- Raw Materials Inventory has a March 31 balance of $87,000.
- Raw materials purchases in April are $580,000, and total factory payroll cost in April is $386,000.
- Actual overhead costs incurred in April are indirect materials, $55,000; indirect labor, $27,000; factory rent, $33,000; factory utilities, $24,000; and factory equipment depreciation, $57,000.
- Predetermined overhead rate is 50% of direct labor cost.
- Job 306 is sold for $695,000 cash in April.
|
Step by Step Solution