Question: Problem 26 You have until 12:00 PM to complete this assignment. Intro Your company is considering two projects and has estimated the following cash flows:

Problem 26 You have until 12:00 PM to complete this assignment. Intro Your company is considering two projects and has estimated the following cash flows: Year Project A Project B 0 - 15,000 -20,000 1 10,000 10,000 2 10,000 16,000 Part 1 Attempt 1/1 for 10 pts. If project B expands your manufacturing capacity by building a separate factory, what is the relevant cash flow for evaluating project B in year 2? 0+ decima Save Part 2 | Attempt 1/1 for 10 pts. If project B replaces an existing factory (project A), what is the relevant cash flow for evaluating project B in year 2? 0+ decima Save Part 3 | Attempt 1/1 for 10 pts. If project B replaces an existing factory (project A), what is the relevant cash flow for evaluating project B in year 0? 0+ decima Save