Question: Problem 3 . 1 7 Time table [ [ Activity , a , m , b , Immediate predecessor / s ] , [

Problem 3.17
Time
\table[[Activity,a,m,b,Immediate predecessor/s],[A,4,8,10,-],[B,2,8,24,A],[C,8,12,16,A],[D,4,6,10,A],[E,1,2,3,B],[F,6,8,20,E, C],[G,2,3,4,E, C],[H,2,2,2,F],[I,6,6,6,F],[J,4,6,12,D, G, H],[K,2,2,3,I, J]]
Draw the network
Find the CP
Find the slack activities and their individual values
Determine the probability if the project is completed in less than equal to 50
 Problem 3.17 Time \table[[Activity,a,m,b,Immediate predecessor/s],[A,4,8,10,-],[B,2,8,24,A],[C,8,12,16,A],[D,4,6,10,A],[E,1,2,3,B],[F,6,8,20,E, C],[G,2,3,4,E, C],[H,2,2,2,F],[I,6,6,6,F],[J,4,6,12,D, G, H],[K,2,2,3,I, J]] Draw