Question: Problem 3 . ( 2 0 points ) Nino Spirelli has constructed the following ( partial ) time - phased MPS record: On hand Week

Problem 3.(20 points)
Nino Spirelli has constructed the following (partial) time-phased MPS record:
On
hand
Week
123456
Forecast 203020302030
Orders 1486
Projected Available balance 5
Available-to-promise
MPS 50505050
a. Complete the record.
b. Are there any problems?
c. Whats the earliest Nino can promise an order for 44 units?
d. Assume that an order for 15 is booked for week 4. Assume the order for 44 units in part
c is not booked; recompute the record.