Question: Problem 3 - 2 3 Vollmer Manufacturing makes three components for sale to refrigeration companies. The components are processed on two machines: a shaper and

Problem 3-23
Vollmer Manufacturing makes three components for sale to refrigeration companies. The components are processed on two machines: a shaper and a grinder. The times (in minutes) required on each machine are as follows:
Machine
The shaper is available for 120 hours, and the grinder is available for 110 hours. No more than 200 units of component 3 can be sold, but up to 1000 units of each of the other components can be sold. In fact, the company already has orders for 600 units of component 1 that must be satisfied. The profit contributions for components 1,2, and 3 are \(\$ 8\),\(\$ 6\), and \(\$ 9\), respectively.
a. Formulate and solve for the recommended production quantities. If the constant is "1" it must be entered in the box.
Let \( C_{1}=\) units of component 1 manufactured
\( C_{2}=\) units of component 2 manufactured
\( C_{3}=\) units of component 3 manufactured The optimal solution is
Profit \(=\$ \)
b. What are the objective coefficient ranges for the three components? If there is no lower or upper limit, then enter the text "NA" as your answer. Enter "0" if your answer is zero.
Interpret the above ranges for company management.
As long as the profit contribution of component 1 is less than \(\$ \) then the optimal solution will not change. As long as the profit contribution of component 2 is between \(\$ \) and \$ then the optimal solution will not change. As long as the profit contribution of component 3 is more than \$ then the optimal solution will not change. The assumption is that only variable(s) will change at a time.
c. What are the right-hand-side ranges? If there is no lower or upper limit, then enter the text "NA" as your answer. If required, round your answers to two decimal places. Interpret the above ranges for company management.
The right-hand-side ranges are the ranges over which the ? for the associated constraints are applicable.
d. If more time could be made available on the grinder, how much would it be worth? Enter "0" if your answer is zero.
\$ , since the dual value is on the grinder at the optimal solution.
e. If more units of component 3 can be sold by reducing the sales price by \(\$ 4\), should the company reduce the price?
?, since at that price it. be profitable to produce any of component 3.
Problem 3 - 2 3 Vollmer Manufacturing makes three

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!