Question: Problem 3 ( 2 5 points ) . You are given a set of n unit - length tasks, i . e . , each

Problem 3(25 points). You are given a set of n unit-length tasks, i.e., each task has length 1. Each task i, for 1in, can start at the earliest possible time ri and must finish by its deadline di. You are asked to schedule a maximum number of tasks within the given constraint so that all the picked tasks can be scheduled without conflicts. Describe your strategy on picking what tasks and how to schedule them. Explain why your strategy works.
 Problem 3(25 points). You are given a set of n unit-length