Question: Problem 3 (20 points) Project X cash flows is given on the timeline below 0 2 3 Project X -$10,000 $6,500 $3,000 $3,000 $1,000 Calculate

 Problem 3 (20 points) Project X cash flows is given on

Problem 3 (20 points) Project X cash flows is given on the timeline below 0 2 3 Project X -$10,000 $6,500 $3,000 $3,000 $1,000 Calculate Project X NPV if WACC=12% Round your answer to the nearest hundredth, have at least two decimal digits and write it in the Answer field. Would you accept or reject the project (write in the textbox below the answer field)? Answer: Give your reasons 1 i B