Question: Problem 3 [ 3 0 pts ] Consider the following two - week ( 1 0 working days ) computer training class: Given the following.
Problem pts
Consider the following twoweek working days computer training class:
Given the following.
Here activity B requires A and D cant starts before completing C Both and D are also necessary
to be completed for activity to be performed. The duration of these activities arse given in the
table above under column 'normal time'.
a Construct the network and find the critical path while showing LEs, and
slacks for all activities.
b Find the crash cost per day for each activity
c Which activity ias should be crashed to meet a project deadline of days with a
minimum coat? Assume partial crashing.
d Find the new cost.
e Is partial crashing an appropriate assumption in this kind of project?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock