Question: Problem 3. 3. A manager wants to assign tasks to workstations as efficiently as possible and achieve an Page 292 hourly output of four units.

Problem 3. 3. A manager wants to assign tasks to
Problem 3. 3. A manager wants to assign tasks to workstations as efficiently as possible and achieve an Page 292 hourly output of four units. The department uses a working time of 56 minutes per hour. Assign the tasks shown in the accompanying precedence diagram (times are in minutes) to workstations using the following rules: a. In order of most following tasks. Tiebreaker, greatest positional weight. b. In order of greatest positional weight. Tiebreaker: most following tasks. c. What is the efficiency