Question: Problem: 3 ( 9 questions ) You are managing a small software development project with 1 0 modules. The project has 3 deliverables, Design, Code,
Problem: questions
You are managing a small software development project with modules. The project has deliverables, Design, Code, and Test that are done sequentially with no overlap and each deliverable takes days. The table below describes each of the deliverables:
Deliverable
Project Budget
Quantity
Rate
Duration
Cost
Design Complete
day
$
Code Complete
day
$
Test Complete
day
$
Total
$
Design and Code are measured by the modules completed and Test is measured by test cases completed of which there are test cases There is no learning curve on this project.
The Project Sponsor has asked you to provide a status report every days using Earned Value. Specifically, the Project Sponsor wants the CPI, SPI, and EAC for the project included in each status report.
Status Report
days into the project, the design team has almost completed the modules. The results are:
Deliverable
After days
Quantity
Cost
Design Complete
$
Code Complete
$
Test Complete
$
Total
$
Status Report
days into the project, the design team is complete, but coding has fallen behind due to some technical problems. The results are:
Deliverable
After days
Quantity
Cost
Design Complete
$
Code Complete
$
Test Complete
$
Total
$
Status Report
days into the project, the test team came through, thanks to overtime, and the project is done on time. The results are:
Deliverable
After days
Quantity
Cost
Design Complete
$
Code Complete
$
Test Complete
$
Total
$
For the first status report, the CPI for project is approximately: a
b
c
d
e
Up till day Design divided by cost
x
CPI
For the first status report, the SPI for the project is
a
b
c
d
e
For the first status report, the EAC for project is approximately: a $
b $
c $
d $
e None of the above
Total Deliverables CPI
For the second status report, the CPI for the project is a
b
c
d
e
For the second status report, the SPI for the project is a
b
c
d
e
For the second status report, the EAC for the project is approximately: a $
b $
c $
d $
e None of the above
For the third status report, the CPI for the project is a
b
c
d
e
GMS Midterm Practice Questions Page
For the third status report, the SPI for the project is a
b
c
d
e
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock