Question: Problem: 3 ( 9 questions ) You are managing a small software development project with 1 0 modules. The project has 3 deliverables, Design, Code,

Problem: 3(9 questions)
You are managing a small software development project with 10 modules. The project has 3 deliverables, Design, Code, and Test that are done sequentially with no overlap and each deliverable takes 10 days. The table below describes each of the deliverables:
Deliverable
Project Budget
Quantity
Rate
Duration
Cost
Design Complete
10
1/day
10
$ 10,000
Code Complete
10
1/day
10
$ 20,000
Test Complete
50
5/day
10
$ 10,000
Total
30
$ 40,000
Design and Code are measured by the modules completed and Test is measured by test cases completed (of which there are 50 test cases). There is no learning curve on this project.
The Project Sponsor has asked you to provide a status report every 10 days using Earned Value. Specifically, the Project Sponsor wants the CPI, SPI, and EAC for the project included in each status report.
Status Report 1
10 days into the project, the design team has almost completed the 10 modules. The results are:
Deliverable
After 10 days
Quantity
Cost
Design Complete
9
$ 10,000
Code Complete
0
$ 1,000
Test Complete
0
$ 1,000
Total
$ 12,000
Status Report 2
20 days into the project, the design team is complete, but coding has fallen behind due to some technical problems. The results are:
Deliverable
After 20 days
Quantity
Cost
Design Complete
10
$ 12,000
Code Complete
8
$ 18,000
Test Complete
0
$ 1,000
Total
$ 31,000
Status Report 3
30 days into the project, the test team came through, thanks to overtime, and the project is done on time. The results are:
Deliverable
After 30 days
Quantity
Cost
Design Complete
10
$ 13,000
Code Complete
10
$ 19,000
Test Complete
50
$ 13,000
Total
$ 45,000
17. For the first status report, the CPI for project is approximately: a.1.00
b.0.90
c.1.11
d.0.75
e.1.20
Up till day 10 Design divided by cost
0.09 x 10,000=9000
CPI =9000/12,000=0.75
18. For the first status report, the SPI for the project is
a.1.00
b.0.90
c.1.11
d.0.75
e.1.20
19. For the first status report, the EAC for project is approximately: a. $40,000
b. $45,000
c. $48,000
d. $53,000
e. None of the above
Total Deliverables / CPI
40000/0.90=5333.33
20. For the second status report, the CPI for the project is? a.1.00
b.0.83
c.0.84
d.0.87
e.1.20
21. For the second status report, the SPI for the project is? a.1.00
b.0.83
c.0.84
d.0.87
e.1.20
22. For the second status report, the EAC for the project is approximately: a. $40,000
b. $45,000
c. $48,000
d. $53,000
e. None of the above
23. For the third status report, the CPI for the project is? a.1.00
b.0.83
c.0.84
d.0.87
e.0.89
GMS450 Midterm Practice Questions Page 6
24. For the third status report, the SPI for the project is? a.1.00
b.0.83
c.0.84
d.0.87
e.1.20

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!