Question: Problem 3: A potential CB project has the following cash flows: CFO = -$500, CF1 = $300, CF2 = $200, CF3 = $150. WACC =
Problem 3: A potential CB project has the following cash flows: CFO = -$500, CF1 = $300, CF2 = $200, CF3 = $150. WACC = 6%. Compute the following: V CPT DPB & NFV CPT (EX) A. Payback Period 3. NPV 86.9610 Accept project 2. IRR 16.4634 76 Accept project