Question: Problem 3 : Accept or Reject Project Your company is considering a project with an initial cash outlay of $ 1 , 0 0 0

Problem 3: Accept or Reject Project
Your company is considering a project with an initial cash outlay of $1,000,000. The discount rate is 10%. Projected cash inflows are: Year 1: $100,000;2) Year 2: $500,000; Year 3: $600,000; Year 4:$700,000; Year 5: $900,000. Required: 1) Compute Net Present Value; 2) Show work; 3) Should you accept or reject the project? ; 4) Why?