Question: Problem 3: Consider a set of three periodic tasks with the execution profiles shown below: Process Arrival Time Execution Time Ending Deadline A(1) 0 10
Problem 3:Consider a set of three periodic tasks with the execution profiles shown below:
| Process | Arrival Time | Execution Time | Ending Deadline |
| A(1) | 0 | 10 | 20 |
| A(2) | 20 | 10 | 40 |
| A(3) | 40 | 10 | 60 |
| ... | ... | ... | ... |
| ... | ... | ... | ... |
| B(1) | 0 | 10 | 50 |
| B(2) | 50 | 10 | 100 |
| B(3) | 100 | 10 | 150 |
| ... | ... | ... | ... |
| ... | ... | ... | ... |
| C(1) | 0 | 15 | 50 |
| C(2) | 50 | 15 | 100 |
| C(3) | 100 | 15 | 150 |
| ... | ... | ... | ... |
| ... | ... | ... | ... |
Develop a set of scheduling diagrams depicting how these jobs will be scheduled using:
A.Fixed-priority scheduling (A has priority over B and B has priority over C)
B.Fixed-priority scheduling (C has priority over B and B has priority over A)
C.Earliest-deadline scheduling