Question: Problem 3 For the project in Problem 2 , assume the task times are variable, with the optimistic, most likely, and pessimistic task times as

Problem 3
For the project in Problem 2, assume the task times are variable, with the optimistic, most likely, and pessimistic task times as follows:
\begin{tabular}{|c|l|c|c|c|}
\hline & & & TASK TIME (DAYS) & \\
\hline TASK & DESCRIPTION & OPTIMISTIC & MOST LIKRLY & PESSIMISTIC \\
\hline A & Inspect the house & 2 & 4 & 5\\
\hline B & Appraise the house & 1 & 3 & 5\\
\hline C & Do the title search & 3 & 4 & 6\\
\hline D & Get the tax clearance & 3 & 5 & 10\\
\hline E & Get the sales permit & 1 & 2 & 2\\
\hline F & Find a buyer & 7 & 21 & 42\\
\hline G & Get a mortgage & 7 & 14 & 30\\
\hline H & Get the legal documents & 5 & 10 & 14\\
\hline I & File the legal documents & 1 & 1 & 1\\
\hline J & Final closing & 1 & 1 & 1\\
\hline
\end{tabular}
a. Compute by hand the earliest expected completion time of the project, identify the critical tasks and path(s), and determine the variance of the project's completion time. (10 points)
b. Use Excel QM to venify your computations in part (a).(5 points)
Problem 3 For the project in Problem 2 , assume

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!