Question: Problem 3 GIVEN: A sanitary sewer line is to be designed to serve a new housing development. When first installed, the initial peak flow is
Problem
GIVEN: A sanitary sewer line is to be designed to serve a new housing development. When first installed, the initial peak flow is estimated as mathrmftmathrmsec but at full buildout the sewer line is expected to accommodate a peak flow of mathrmftmathrmsec
REQUIRED: Answer the following questions.
a Determine the minimum diameter for a commerciallyavailable pipe.
b Determine the minimum slope for a commerciallyavailable pipe.
c If the existing infrastructure limits the slope of the sewer line to what would you recommend as the design engineer?