Problem
The following information is given:
tableTaskPerformance time minutestableTask must followthis taskABACBDBECFCGD E FHG
The assembly line has an minute cycle time.
a Draw the precedence diagram.
b Determine the number of workstations.
c Assign the tasks
d Calculate the efficiency.