Question: Problem 3 . The following project is at the end of its 6 th week. Find the cost and schedule variances. Also find the CPI

Problem 3. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods.

Activity

Predecessor

Duration (wks)

Budget ($)

Actual Cost ($)

%Complete

a

-

2

600

400

100

b

-

3

150

180

100

c

a

2

250

300

100

d

a

5

500

400

20

e

b, c

4

400

200

20

CV =

SV =

CPI =

SPI=

CR=

EAC=

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!