Question: Problem 3 The following table gives the completion time in minutes of the first two units by four workers: A, B, C, and D. Estimate
Problem 3 The following table gives the completion time in minutes of the first two units by four workers: A, B, C, and D. Estimate the number of repetitions each of the four workers will require to achieve a desired standard time of 20 minutes.
| Worker | Completion Time (minutes) | ||
| 1st Unit | 2nd Unit | ||
| A | 40.0 | 28.0 | |
| B | 42.5 | 38.3 | |
| C | 53.5 | 40.1 | |
| D | 47.0 | 37.6 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts