Question: Problem 3 The product development group of a tech company has been working on a new computer software program. The activities, their immediate predecessors, and
Problem
The product development group of a tech company has been working on a new computer software program. The activities, their immediate predecessors, and time estimates in weeks for the software development project are given in the following table:
tableActivitytableImmediatePredecessorsTime weeksOptimisticMost Likely,PessimisticABABDEBBII,
a Calculate the expected durations and the variance or standard deviation for each activity.
b Applying PERT, find the expected project completion time and the project standard deviation?
c What is the probability likelihood that the project will be completed so that the company may introduce the new product within weeks?
d If you wanted to be confident of completing the project on time, what would be its completion time target?PLEASE SHOW ALL WORK!!
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock