Question: Problem 3 The product development group of a tech company has been working on a new computer software program. The activities, their immediate predecessors, and

Problem 3
The product development group of a tech company has been working on a new computer software program. The activities, their immediate predecessors, and time estimates (in weeks) for the software development project are given in the following table:
\table[[Activity,\table[[Immediate],[Predecessors]],Time (weeks)],[Optimistic,Most Likely,Pessimistic],[A,-,3,4,5],[B,A,3,3.5,7],[C,B,4,5,6],[D,C,2,3,4],[E,B,5,9,13],[F,B,7.5,8.5,12.5],[G,E,4.5,6,7.5],[H,E,5,6,13],[I,D,G,2,2.5,6],[J,F,H,I,4,5,6]]
a. Calculate the expected durations and the variance (or standard deviation) for each activity.
b. Applying PERT, find the expected project completion time and the project standard deviation?
c. What is the probability (likelihood) that the project will be completed (so that the company may introduce the new product) within 32 weeks?
d. If you wanted to be 99% confident of completing the project on time, what would be its completion time target?PLEASE SHOW ALL WORK!!
 Problem 3 The product development group of a tech company has

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!