Question: PROBLEM 3 Using CPM / PERT , find the minimum number of days to finish the project. For each activily, find out the earliest start

PROBLEM 3
Using CPM/PERT, find the minimum number of days to finish the project. For each activily, find out the earliest start and finish time and the latest start and finish time. (Use one week equal to 5 days)
\table[[Activity,Predecessor,Duration],[A,-,4 days],[B,A,6 days],[C,A,4 days],[B,C,1 Week],[E,B,C,6 days],[F,E,2 Weeks]]