Question: Problem 3.28 - Bookmatch Problem The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations,
| Problem 3.28 - Bookmatch |
| Problem The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: |
| Activity | Duration (weeks) | Precedes | Crash Cost/Week |
| A (start) | 1 | B, C | $ 400 |
| B | 1 | E | $ 100 |
| C | 4 | F | $ 200 |
| E | 2 | F | $ 300 |
| F (end) | 2 | long dash | $ 400 |
Suppose that Rafay is only given 5 weeks (instead of7) to complete the project. By how many weeks should each activity be crashed in order to meet thedeadline? Assume that you can crash an activity down to 0 weeks duration.
| Each Activity Should be Reduced BY (days) | ||
| A | ? | ||
| B | ? | ||
| C | ? | ||
| E | ? |
| D | ? |