Question: Problem 3.28 - Bookmatch Problem The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations,

Problem 3.28 - Bookmatch

Problem The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week:

Activity

Duration (weeks)

Precedes

Crash Cost/Week

A (start)

1

B, C

$ 400

B

1

E

$ 100

C

4

F

$ 200

E

2

F

$ 300

F (end)

2

long dash

$ 400

Suppose that Rafay is only given 5 weeks (instead of7) to complete the project. By how many weeks should each activity be crashed in order to meet thedeadline? Assume that you can crash an activity down to 0 weeks duration.

Activity

Each Activity Should be Reduced BY

(days)

A ?
B ?
C ?

E

?
D ?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!