Question: Problem 4 - 1 7 Bragg's Bakery is building a new automated bakery in downtown Sandusky. Here are the activities that need to be completed
Problem
Bragg's Bakery is building a new automated bakery in downtown Sandusky. Here are the
activities that need to be completed to get the new bakery built and the equipment
installed.
b Identify the critical path.
ACDF
ABDF
b What is the normal project length?
Normal project
weeks
length
c What is the project length if all activities are crashed to their minimum?
Project length
weeks
d Bragg's loses $ in profit per week for every week the bakery is not completed.
How many weeks will the project take if we are willing to pay crashing cost as long
as it is less than $ for crashing individual activity?
The project will take
weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer