Question: Problem 4 - 1 8 ( Static ) The following CPM network has estimates of the normal time in weeks listed for the activities: A
Problem Static
The following CPM network has estimates of the normal time in weeks listed for the activities:
A network diagram flowchart. The flows are as follows. A B D F and G A C D E and G A B D E and G
a Identify the critical path.
multiple choice
ACDFG Correct
ABDEG
ABDFG
ACDEG
b What is the length of time to complete the project?
c Which activities have slack, and how much?
multiple choice
C weeks; F weeks.
C week; E weeks.
D week; E weeks.
B weeks; E weeks. Correct
Here is a table of normal and crash times and costs.
ACTIVITY NORMAL TIME CRASH TIME NORMAL COST CRASH COST
A $ $
B
C
D
E
F
G
d Which activities would you shorten to cut two weeks from the schedule in a rational fashion?
multiple choice
B C
A C Correct
A E
B D
d What would be the total incremental cost?
d Is the critical path changed?
multiple choice
Yes
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock