Question: Problem 4 . 1 Given a flow rate of 8 5 0 0 m 3 d and an overflow rate of 5 0 m 3

Problem 4.1
Given a flow rate of 8500m3d and an overflow rate of 50m3dm2, calculate the following
design parameters of a proposed circular primary sedimentation tank:
(i) Height of the sedimentation tank (assuming a criterion of diameter/height ratio of 3.5)
(2 marks)
(ii) Hydraulic retention time (HRT) of the sedimentation tank. (1 mark)
Problem 4.2
There is an outdoor renovation project ongoing next to the lobby (GF) of one of the hall in
HKUST. You are a civil engineering student living in the hall and would like to estimate the
noise level at your room. Give your answers to the nearest dB for this question.
(i) Someone claimed that under the same noise source, if receiving distance is doubled,
the sound pressure level would be attenuated by approximately 6dB. Do you agree? (Hint:
Assuming two receivers with distances and sound levels r1,L1 and r2,L2 respectively and prove
the relationship above.)(2 marks)
(ii) Hence, if you are living on the 8th floor, and the measured noise level under unmitigated
scenario is 98dB on the 2nd floor, what is the estimated noise level at your room without any
mitigation measures? (2 marks)
(iii) Suggest one engineering solution that the can be taken to minimize the noise impact to
the residents in the hall. (2 marks)
Problem 4 . 1 Given a flow rate of 8 5 0 0 m 3 d

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!