Question: Problem 4 (12 points) Figure 1. Parts Moved Between Work Centers A B C D A 60 70 0 B 100 20 0 C 0
Problem 4 (12 points)
| Figure 1. Parts Moved Between Work Centers | ||||||||||||||||
| A | B | C | D | |||||||||||||
| A | 60 | 70 | 0 | |||||||||||||
| B | 100 | 20 | 0 | |||||||||||||
| C | 0 | 0 | 80 | |||||||||||||
| D | 0 | 0 | 0 | |||||||||||||
|20'|20'|20'| | ||||||||||||||||
a) For the existing layout, determine the cumulative "loaddistance" or "movement cost". Assume it costs $2.00 to move 1 piece 1 foot. You must show all work to get credit for the problem.