Question: Problem 4 (20 marks): Construct a project network for the following project and identify the critical path using a forward and a backward pass method.

Problem 4 (20 marks): Construct a project network
Problem 4 (20 marks): Construct a project network for the following project and identify the critical path using a forward and a backward pass method. Precedence Activities ES LS EF LF Slack Critical Path? Activity A B D E F G H B AC B B DE F Activity Time (weeks) 8 2 5 3 7 5 12 10