Question: Problem 4 ( 3 5 POINTS ) a . Complete the earthwork calculations sheet below and plot the resulting mass diagram. Divide Total Fill (

Problem 4
(35 POINTS)
a. Complete the earthwork calculations sheet below and plot the resulting mass diagram. Divide Total Fill (CCY) by 0.9 to convert to Adjusted Fill (BCY).
b. What quantity of material must be hauled along the length of the project?
c. What is the average haul distance, in stations, for this material?