Question: Problem 4 . 4 Given the following product tree, explode, offset, and calculate the gross and net requirements. All lead times are one week, and
Problem Given the following product tree, explode, offset, and calculate the gross and net requirements. All lead times are one week, and the quantities required are shown in parentheses. The MPS calls for completion of Js in week There is a scheduled receipt of Ks in week There are Ls and Ns on hand.
Item Week
Number
Gross requirements
Scheduled receipts
J Projected available
Net requirements
Planned order receipt
Planned order release
Gross requirements
Scheduled receipts
K Projected available
Net requirements
Planned order receipt
Planned order release
Gross requirements
Scheduled receipts
L Projected available
Net requirements
Planned order receipt
Planned order release
Gross requirements
Scheduled receipts
M Projected available
Net requirements
Planned order receipt
Planned order release
Gross requirements
Scheduled receipts
N Projected available
Net requirements
Planned order receipt
Planned order release
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock