Question: problem 4: (40 points) Please solve the network diagram provided in the problem, i.e., calculate ES, EF, FF, TF, LS, and LF for all activities.

 problem 4: (40 points) Please solve the network diagram provided in

the problem, i.e., calculate ES, EF, FF, TF, LS, and LF for

problem 4: (40 points) Please solve the network diagram provided in the problem, i.e., calculate ES, EF, FF, TF, LS, and LF for all activities. These numbers may be provided in a network or in a table. Then, please implement the resource leveling method *completely* showing the improvement factor calculations used. B D 5 5 3R 2R A F 1R 2R C m 3 4R 5R