Question: Problem 4 - 5 ( Algo ) Your project to obtain charitable donations is now 4 9 days into a planned 5 9 - day
Problem Algo
Your project to obtain charitable donations is now days into a planned day project. The project is divided into activities. The
first activity is designed to solicit individual donations. It is scheduled to run the first days of the project and to bring in $
Even though we are days into the project, we still see that we have only of this activity complete. The second activity relates to
company donations and is scheduled to run for days starting on day and extending through day We estimate that, even
though we should have of this activity complete, it is actually only complete. This part of the project was
scheduled to bring in $ in donations. The final activity is for matching funds. This activity is scheduled to run the last days of
the project and has not started. It is scheduled to bring in an additional $ So far, $ has actually been brought in on the
project.
Calculate the Schedule Variance, Schedule Performance Index, and Cost actually value in this case Performance Index. Hint: Note
that this problem is different since revenue rather than cost is the relevant measure. Use care in how the measures are interpreted.
Note: Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values.
Round your "performance index" values to decimal places.
Schedule Variance
Schedule Performance Index
Cost Variance
Cost Performance Index
Step by Step Solution
There are 3 Steps involved in it