Question: Problem 4 - 6 ( Algo ) A project to build a new bridge seems to be going very well because the project is well

Problem 4-6(Algo)
A project to build a new bridge seems to be going very well because the project is well ahead of schedule and costs seem to be
running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity
is 65 percent complete. The planners were expecting to be only 52 percent through the third activity at this time. The first activity
involves prepping the site for the bridge. It was expected that this would cost $1,416,000 and it was done for only $1,296,000. The
second activity was pouring concrete for the bridge. This was expected to cost $10,496,000 but was actually done for $8,996,000.
The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,496,000. To
date, they have spent $4,996,000 on the superstructure.
Calculate the Schedule Variance, Schedule Performance Index, and Cost Performance Index for the project to date.
Note: Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values.
Round your "performance index" values to 3 decimal places.
Schedule Variance
Schedule Performance Index
Cost Performance Index
 Problem 4-6(Algo) A project to build a new bridge seems to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!