Question: Problem 4 ) 6 Points ( - 2 ? error ) A manufacturing company operates 1 0 hours per day for 2 5 0 days

Problem 4)6 Points (-2? error)
A manufacturing company operates 10 hours per day for 250 days per year and uses one type of
machine. Use the Machine Requirement Planning tool and information below to determine how many
machines will be needed to meet annual demand for these products. Show your work in the table below.
Round the Annual Processing Times to one decimal. Round the number of machines UP to the
closest integer value.
NR=i=1kpiDiT
Total Number of Machines Needed:
 Problem 4)6 Points (-2? error) A manufacturing company operates 10 hours