Question: Problem 4 - 7 ( Static ) The following activities are part of a project to be scheduled using CPM: ACTIVITYIMMEDIATE PREDECESSORTIME ( WEEKS )

Problem 4-7(Static)
The following activities are part of a project to be scheduled using CPM:
ACTIVITYIMMEDIATE PREDECESSORTIME (WEEKS)A6BA3CA7DC2EB, D4FD3GE, F7
b. What is the critical path?
multiple choice
A-C-D-E-G
A-C-D-F-G
A-B-E-G
c. How many weeks will it take to complete the project?
d. How much slack does activity B have?