Question: Problem 4 - 8 ( Algo ) Schedule the following activities using CPM: ACTIVITYIMMEDIATE PREDECESSORTIME ( WEEKS ) A 3 BA 4 CA 9 DB

Problem 4-8(Algo)
Schedule the following activities using CPM:
ACTIVITYIMMEDIATE PREDECESSORTIME (WEEKS)A3BA4CA9DB2EC
D7FD3GF4HE
G5
b. What is the critical path?
multiple choice 1
A-B-D-F-G-H
A-C-E-H
A-C-E-F-G-H
A-B-D-E-H
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
multiple choice 2
B 3 weeks C 2 weeks F 1 week H 2 weeks.
B 2 weeks C 3 weeks E 4 weeks H 1 week.
B 3 weeks D 3 weeks F 3 weeks G 3 weeks.