Question: Problem 4 - 8 ( Algo ) Schedule the following activities using CPM: ACTIVITYIMMEDIATE PREDECESSORTIME ( WEEKS ) A 3 BA 4 CA 9 DB
Problem Algo
Schedule the following activities using CPM:
ACTIVITYIMMEDIATE PREDECESSORTIME WEEKSABACADBEC
DFDGFHE
G
b What is the critical path?
multiple choice
ABDFGH
ACEH
ACEFGH
ABDEH
c How many weeks will it take to complete the project?
d Which activities have slack, and how much?
multiple choice
B weeks C weeks F week H weeks.
B weeks C weeks E weeks H week.
B weeks D weeks F weeks G weeks.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
