Question: Problem 4 - 9 ( Algo ) The R&D department is planning to bid on a large project for the development of a new communication
Problem Algo
The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, times, and sequences required.
ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B A
C A
D A
E B
F C D
G D F
H D
I E G H
b What is the critical path?
Note: You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.
check all that apply
ACFGI
ABEI
ADHI
ADFGI
c Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B C D and G each one week. Which would you shorten?
Note: You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.
check all that apply
B
C
D
G
E
F
d What is the new critical path?
Note: You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.
check all that apply
ACFGI
ABEI
ADHI
ADFGI
d What is the earliest completion time for the new critical path?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock