Question: Problem 4 - 9 ( Algo ) The R&D department is planning to bid on a large project for the development of a new communication

Problem 4-9(Algo)
The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, times, and sequences required.
\table[[ACTIVITY IMMIEDIATE PREDECESSOR,TIME (WEEKS),],[A,-,6],[B,A,3],[C,A,4],[D,B,4],[E,C, D,3],[F,D, F,3],[G,D,2],[H,E, G, H,3],[I,,5]]
b. What is the critical path?
Note: You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.
A-C-F-G-1
A-B-E-1
A-D-H-1
A-D-F-G-1
c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten?
Note: You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.
B
c
D
G
d-1. What is the new critical path?
Note: You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.
A-C-F-G-I
A-B-E-1,
A-D-H-H
A.D-F-G-I
d-2. What is the earliest completion time for the new critical path?
Completion time
weeks
This is a numeric cell, so please
enter numbers only:
 Problem 4-9(Algo) The R&D department is planning to bid on a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!