Question: Problem 4: A new contract was written with Company B with the following stipulations: Cpk = 1.2 , Specification Nominal (N) = 10 + 0.5
Problem 4: A new contract was written with Company B with the following stipulations: Cpk = 1.2 , Specification Nominal (N) = 10 + 0.5 mils. Company B wants to design their process by setting the process average = 10 mils and the sample size (n) = 50 . Find: Xdouble bar: _______ UCLx: _______ LCLx: _______ Rbar: _______ UCLr: _______ LCLr: _______ Reject Rate: _______ ppm